요약

The Housing Grants, Construction and Regeneration Act 1996 (commonly called 'the Construction Act') introduced statutory adjudication and payment provisions for construction contracts. Part II provides a right to refer disputes to adjudication at any time, and regulates interim payments through payment and pay-less notices. It was substantially amended by the Local Democracy, Economic Development and Construction Act 2009.

핵심 포인트

  • Right to adjudication: any party to a construction contract may refer a dispute to adjudication at any time (s.108)
  • Adjudicator must reach a decision within 28 days (extendable by 14 days with consent)
  • Payment provisions: adequate mechanism for determining payments and due dates (s.110)
  • Payment notices and pay-less notices required within prescribed periods (ss.110A, 111)
  • Right to suspend performance for non-payment (s.112)
  • Applies to construction operations as defined, with exclusions for certain contracts

편과 조

개정 이력

2009Local Democracy, Economic Development and Construction Act 2009

Substantially amended payment provisions, introduced pay-less notices, extended adjudication rights, and removed the requirement for construction contracts to be in writing.