The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022

The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022

Independent editorial summary — not the official statute text. Read the official version on legislation.gov.uk.

Type: UK Statutory Instrument

Year: 2022

Number: 1396

Made: 2022-12-07

Coming into force: 2022-12-29

Last ingested: 2026-06-12 from legislation.gov.uk.

Read the full text on legislation.gov.uk

Explanatory note

Reproduced verbatim from the instrument as published on legislation.gov.uk (Crown Copyright, Open Government Licence v3.0). The note is prepared by the responsible government department and is not part of the instrument itself.

This Order authorises the undertaker (referred to in this Order as the undertaker) to construct, operate and maintain a power generating station and carbon capture and compression plant. The Order permits the undertaker to acquire, compulsorily or by agreement, land and rights in land and to use land for this purpose.

The Order also grants a deemed marine licence under Part 4 of the Marine and Coast Access Act 2009.

A copy of the Order plans and the book of referenced mentioned in this Order and certified in accordance with Article 41 (certification of plans, etc.) may be inspected free of charge during working hours at Crowle Library, The Market Hall, Market Place, Crowle, North Lincolnshire, DN17 4LA.