The Rivenhall Generating Station Extension Order 2024

The Rivenhall Generating Station Extension Order 2024

Independent editorial summary — not the official statute text. Read the official version on legislation.gov.uk.

Type: UK Statutory Instrument

Year: 2024

Number: 1391

Made: 2024-12-19

Coming into force: 2024-12-20

Last ingested: 2026-06-12 from legislation.gov.uk.

Read the full text on legislation.gov.uk

Explanatory note

Reproduced verbatim from the instrument as published on legislation.gov.uk (Crown Copyright, Open Government Licence v3.0). The note is prepared by the responsible government department and is not part of the instrument itself.

This Order authorises Indaver Rivenhall Limited (referred to in this Order as the undertaker) to construct an extension to an energy from waste generating station at Rivenhall, Essex, previously authorised by planning permission under the 1990 Act, and to operate the extended generating station at a capacity of over 50 MW.